# The North Dakota Town Where Data Centers Won 

Harwood was alone among 41 localities in voting down new restrictions.

November 13, 2026 • Commentary 

By [Travis Fisher](https://www.cato.org/people/travis-fisher) 

This article appeared in [*The Wall Street Journal* ](https://wsj.com)on November 13, 2026.

Data-center developers took a beating on Nov. 3. In 40 of 41 local ballot measures across 10 states, voters favored restrictions on new [data centers](https://www.wsj.com/topics/industry/data-centers) or rejected proposals that would spur development. Some towns proposed outright bans while others erected zoning or regulatory barriers.

Harwood, N.D., was the exception. The city of around 800 will host a $3 billion, 280-megawatt data center developed by [Applied Digital](https://www.wsj.com/market-data/stock/apld?mod=article_chiclet). Voters overwhelmingly rejected a charter amendment that would have required independent reviews and public hearings before city approval of new “industrial developments,” including data centers. (The initiative wouldn’t have affected the Applied Digital project, which was approved in 2025.) The measure wasn’t a moratorium, but Mayor Blake Hankey warned that it would be “financially burdensome” and restrict development beyond data centers.

How did Harwood overcome the anti-data-center wave? The project’s economic benefits were clear. Business Insider reports that Applied Digital hopes to employ 200 people. The new campus will generate significant revenue from property and sales taxes, Mr. Hankey said.

The local electric co-op took steps to shield existing customers from project costs. Cass County Electric Cooperative says Applied Digital must pay for engineering studies assessing the project’s impact on the electric grid around Harwood, make transmission improvements, and build a new substation to serve the facility. The co-op has also secured prepayments and irrevocable letters of credit to protect existing customers from cost increases.

For many Americans, concerns about data centers’ effect on their electric bills outweigh the promised economic benefits. A September AP-NORC and University of Chicago poll found 63% of Americans worried data centers would increase electricity prices. Seventy-three percent supported requiring developers to pay for grid upgrades.

Harwood was alone among 41 localities in voting down new restrictions.

Yes, data centers are electricity guzzlers, and the infrastructure required to serve them is costly. If a developer promises to buy hundreds of megawatts of power but later cancels or scales back, utility customers could be left to foot the bill.

Regulators also have limited ability to shield customers from data center costs on a shared grid. A large transmission line built for a data center will serve other customers, making it difficult to determine how its costs should be divided. Even well-designed utility contracts can’t eliminate every disagreement over who should pay for infrastructure costs.

An emerging solution is allowing data centers to build their own grid. A private grid would connect a data center directly to a dedicated power plant without relying on a regulated utility network. Developers could build these systems or contract with private suppliers, with investors paying for the infrastructure and bearing the financial risk if the project fails. Since the new grid would operate independently, regulators wouldn’t have to determine how much of the construction costs should be passed on to other customers.

This is the Harwood model on a larger scale. Would Americans feel differently about hosting data centers in their community if they knew the project wouldn’t increase their electric bills?

Ohio, Utah, New Hampshire and West Virginia have already taken steps to exempt off-grid electricity providers from traditional utility regulation. Other states should follow their example. Local concerns about water consumption, noise, and land use still warrant scrutiny, but ratepayers shouldn’t be forced to finance an industry’s electricity needs.

State and local governments should work with data-center developers to regain public trust. Developers can start by paying for grid upgrades or securing their own power. Without a solution to insulate people from data center costs, electoral backlash is sure to continue.

##### About the Author 

[![Travis Fisher - cropped](/sites/cato.org/files/styles/author_picture/public/2023-09/travis-fisher-cropped.jpg?itok=wFuUAHy-)](/people/travis-fisher) 

##### [Travis Fisher](/people/travis-fisher)

Director of Energy and Environmental Policy Studies, Cato Institute

[ 

](https://x.com/ts_fisher)